A task is completed by 30 persons in 4 days. In how many days the same will be completed by 40 persons? REASON.

Respuesta :

sarajevo
sarajevo sarajevo
  • 03-08-2018

As per the given data

A task is completed by 30 persons in 4 days

we are supposed to find In how many days the same will be completed by 40 persons

Task is completed by 30 persons in 4 days, it mean

30 person does one fourth of the work in one day

1 person does [tex] \frac{1}{4*30}=\frac{1}{120}th [/tex] of the work in one day

So back to previous step,

work done by 40 person in one day =[tex] 40*\frac{1}{120} =\frac{1}{3} [/tex]

Hence the number of days required to complete the work by 40 person =3

Answer Link

Otras preguntas

Please help me out with this
order the following from greatest to least0.03 1.01 0.9 0.905​
Solve 11cW+ 2k= 15cwfor k.
The deflection of wind due to the coriolis effect is strongest at _____. the equator the poles the midlatitudes midnight
How did this technology make the eqyptian revolution different from earlier revolutions elsewhere in the world?
Science Questionif the parent hydra has 32 chromosomes, how many chromosomes does the hydra offspring have?
Which angle pairs are supplementary? Check all that apply.
Which of these is the accessory organ to digestion that produces most of the digestive enzymes?
PERGUNTA 6 A sociedade humana é composta por organizações que fornecem os meios para o atendimento das necessidades das pessoas. Serviços de Saúde, água e energ
Find the odds of an answer if the probability of the event is given to be 3/8 A. 5:3 B. 3/8 C. 5/8 D. 3:5